Sellersville Borough Paving Schedule
Paving will begin next week in the Borough. The tentative schedule is as follows:
(Please note this is subject to change)
Monday, October 24th - Edge Mill Clipper Way, Jefferson Drive, and Adams Way
Tuesday, October 25th thru Wednesday, October 26th - Mill Franklin Avenue and 12th Street
Thursday, October 27th thru Friday, October 28th - Over excavate & base in Franklin Avenue
Monday, October 31st - Pave Clipper Way (possibly Adams Way)
Tuesday, November 1st - Pave Franklin Avenue
Wednesday, November 2nd - Pave 12th Street
Thursday, November 3rd - Pave Jefferson Drive